STATE-LEVEL EIA DECISIONS

    Descrizione 1
    Update date
    Authors

    Anna Cacciuni, Caterina D'Anna

    Abstract
    Immagine
    Abstract

    The indicator shows the yearly trend in the number of projects under state jurisdiction subject to Environmental Impact Assessment (EIA), the annual distribution of the outcomes of environmental compatibility decisions, and their breakdown by type of infrastructure. It reflects the central public administration's response regarding decision-making processes related to environmental impact assessments.

    In 2023, out of 141 projects evaluated, 122 positive EIA decisions with environmental conditions and 19 negative ones were issued.

    Description

    The Environmental Impact Assessment (EIA) is the process that includes, in accordance with the provisions set out in Title III, Part Two of Legislative Decree 152/2006 and subsequent amendments, the preparation and submission of the Environmental Impact Study by the project proponent, the conduct of public consultations, the evaluation of the Environmental Impact Study and any additional information provided by the proponent, the results of the consultations, the adoption of the EIA decision regarding the environmental impacts of the project, and the integration of the EIA decision into the project’s approval or authorization measure.

    The indicator represents the number of EIA decisions (EIA decrees) under state jurisdiction issued annually by the Ministry of the Environment and Energy Security (MASE), in agreement with the Ministry of Culture (MiC). The EIA decision is a “reasoned, mandatory, and binding measure that expresses the conclusion of the competent authority regarding the significant and adverse environmental impacts of the project, adopted on the basis of the conducted evaluation, the results of the public consultations, and any cross-border consultations".

    Purpose

    To describe the yearly trend in the number of projects subject to EIA as established by current regulations, the annual breakdown of environmental compatibility rulings, and their distribution according to the type of works involved.

    The main objective is to provide information on the central public administration’s decision-making response in relation to EIA procedures.

    Policy relevance and utility for users
    Be either national in scope or applicable to regional environmental issues of national significance
    Able to show trend over time
    Be simple, easy to interpret
    Provide a representative picture of environmental conditions, pressures on the environment or society's responses;
    Analytical soundness
    Be based on international standards and international consensus about its validity;
    Be theoretically well founded in technical and scientific terms
    Presents reliability and validity of measurement and data collection methods
    Temporal comparability
    Spatial comparability
    Measurability (data)
    Adequately documented and of known quality
    Updated at regular intervals in accordance with reliable procedures
    An “adequate” spatial coverage
    An “appropriate” temporal coverage
    Main regulatory references and objectives
    • Directive 85/337/EEC of 27 June 1985
    • Directive 97/11/EC of 3 March 1997 amending Directive 85/337/EEC
    • Directive 2011/92/EU of 13 December 2011
    • Directive 2014/52/EU of the European Parliament and of the Council of 16 April 2014
    • Legislative Decree 152/2006, as amended
    • Legislative Decree 104/2017
    • Decree Law 34/2020, converted into Law 77/2020
    • Decree Law 76/2020, converted into Law 120/2020
    • Decree Law 77/2021, converted into Law 108/2021
    • Decree Law 92/2021
    • Law No. 25 of 2022
    • Law No. 91 of 2022
    • Law No. 6 of 2023
    • Decree Law No. 13 of 2023
    DPSIR
    Response
    Indicator type
    Descriptive (A)
    Limitations

    The indicator does not include projects subject to regional EIA procedures.

    Further actions

    Elaborazione dello stesso indicatore a livello regionale.

    Data collection frequency
    Yearly
    Fonte dei dati
    Ministero dell’Ambiente e della Sicurezza Energetica
    Ministero della cultura (MiC)
    Data availabilty

    The EIA measures are available on the MASE Environmental Assessments portal, where all decisions are published: https://va.mite.gov.it/it-IT/Procedure/Provvedimenti

    Spatial coverage

    National

    Time coverage

    June 1989- 2023

    Processing methodology

    Each state-level EIA decision (VIA decree) was collected and analyzed. Starting from the EIA decisions published on MASE’s website, data were compiled on the total number of decisions (positive, negative, negative-interlocutory, and archived) issued each year. Extensions of the validity of existing EIA decisions were not included.

    Update frequency
    Year
    Qualità dell'informazione

    The data are accessible, timely, and complete with good temporal coverage. The indicator is simple, easy to interpret, and highly comparable across time and space due to the consistent data collection methodology.

    State
    Good
    Trend
    Positive
    State assessment/description

     The types of projects subject to state-level EIA have evolved over the years in response to changes in European directives and national legislation.
    In 2023, 141 projects were evaluated, resulting in 122 positive EIA decisions with conditions and 19 negative decisions (Table 1).

    Trend assessment/description

    Between June 1989 and 2023, 1,461 projects were reviewed, resulting in:

    • 1,136 positive EIA decisions,
    • 159 negative decisions,
    • 69 negative-interlocutory decisions,
    • 97 archived.

    Over the last 10 years, the annual average number of EIA decisions (59) has exceeded the 35-year historical average (42), indicating growing attention to sustainable and economic development.

    Comments

    Over 35 years, EIA procedures ended positively for approximately 78% of submitted projects (Figure 2).

    Breakdown of positive decisions by project type (June 1989–2023):

    • 25% (286): Highways/Roads, Airports, Railway segments
    • 17% (189): Thermoelectric/Hydroelectric plants, onshore and offshore wind farms
    • 10% (109): Hydrocarbon exploration and production (onshore and offshore)
    • 10% (110): Port masterplans, Ports, Freight terminals
    • 6% (69): Gas pipelines
    • 5% (60): Power lines
    • 10% (115): Waste, quarries, and special projects (now subject to regional EIA)
    • 17% (198): Other types: nuclear plants, refineries, photovoltaics, steelworks, integrated chemical plants, CO₂ storage, geothermal, mineral extraction, storage of chemicals/gas/fuels, dams/reservoirs, gas storage in natural underground cavities, etc.
    Data
    Headline

    Tabella 1: Numero totale di provvedimenti VIA di competenza statale con esito positivo, negativo e interlocutorio negativo

    Data source

    Elaborazione ISPRA su dati MASE

    Data legend

    a Interviene quando si verifica la sostanziale carenza di informazioni nella documentazione presentata tale da non consentire di esprimere un giudizio circa la compatibilità del progetto. Questa tipologia è presente fino all'emanazione del D.Lgs. 128/2010 di modifica del D.Lgs. 152/2006

    b provvedimento archiviato: quando il proponente non trasmette la documentazione integrativa entro il termine stabilito nella comunicazione della direzione VA del MiTE. Scaduto tale termine, ovvero, qualora dall’esito della verifica la documentazione risulti ancora incompleta, l’istanza risulta archiviata

    Note

     Negli anni sono stati emanati provvedimenti di proroga della validità di provvedimenti già emanati che non sono stati

    Headline

    Tabella 2: Numero di provvedimenti positivi per tipologie d'opera codificate dal D.Lgs. 104/2017

    Data source

    Elaborazione ISPRA su dati MASE

    Thumbnail
    Headline

    Figura 1: Numero totale di provvedimenti VIA di competenza statale

    Data source

    Elaborazione ISPRA su dati MASE

    Thumbnail
    Headline

    Figura 2: Ripartizione per esito dei provvedimenti VIA di competenza statale

    Data source

    Elaborazione ISPRA su dati MASE
     

    Thumbnail
    Headline

    Figura 3: Ripartizione dei provvedimenti di VIA di competenza statale per tipologia d'opera codificate dal D.Lgs. 104/2017

    Data source

    Elaborazione ISPRA su dati MASE